Testing Checklist: 

1 Prepare System and Acceptance Tests
Start Acceptance test Creation
3 Identify test team
Prepare Workplan
5 Prepare test Approach
6 Link Acceptance Criteria and Requirements to form the basis of
acceptance test
Use subset of system test cases to form requirements portion of
acceptance test
8 Prepare scripts for use by the customer to demonstrate that the system meets
requirements
9 Prepare test schedule. Include people and all other resources.
10 Conduct Acceptance Test
11 Start System Test Creation
12 Identify test team members
13 Prepare Workplan
14 Determine resource requirements
15 Identify productivity tools for testing
16 Determine data requirements
17 Reach agreement with data center
18 Prepare test Approach
19 Identify any facilities that are needed
20 Obtain and review existing test material
21 Prepare inventory of test items
22 Identify Design states, conditions, processes, and procedures
23 Determine the need for Code based (white box) testing. Identify conditions.
24 Identify all functional requirements
25 End inventory creation
26 Start test case creation
27 Prepare test cases based on inventory of test items
28 Identify logical groups of business function for new sysyem
29 Divide test cases into functional groups traced to test item inventory  1.30 Design data sets to correspond to test cases
31 End test case creation
32 Review business functions, test cases, and data sets with users
33 Get signoff on test design from Project leader and QA
34 End Test Design
35 Begin test Preparation
36 Obtain test support resources
37 Outline expected results for each test case
38 Obtain test data. Validate and trace to test cases
39 Prepare detailed test scripts for each test case
40 Prepare & document environmental set up procedures. Include back up and
recovery plans
41 End Test Preparation phase
42 Conduct System Test
43 Execute test scripts
44 Compare actual result to expected
45 Document discrepancies and Prepare problem report
46 Prepare maintenance phase input
47 Re-execute test group after problem repairs
48 Prepare final test report, include known bugs list
49 Obtain formal signoff